Perojek Kemasin Semerak Phase II Stage III - Review Phase - Supplementary Report (Volume 3)
- Perunding Bakti - Perunding Bersatu JV 2001
- Various paging,illust,30cm
1.0. Background. 2.0. Schemes Visited: 2.1. Tendo District Irrigation Scheme. 2.2. Monou Irrigation Scheme. 3.0. Findings: 3.1. Irrigation System. 3.2. Water Management. 3.3. Hydraulic Issues. 3.4. Social Issues. 4.0. Conclusion: 4.1. Pipe Irrigation Concept & Design. 4.2. Planning, Implementation and Operation/Maintenance. 4.3. Farmer's Participation and Involvement. 4.4. Land Consolidation & Estate Management.
eng
IRRIGATION.
CONSTUDY.
Review.
Malaysia, Kelantan.